# Excavation begins on the A19 triple-deck junction

> In March 2017, the £75m A19 junction in North Tyneside was 70% complete as crews began removing about 80,000 cubic metres of soil for the new underpass.

Page URL: https://ctep.ca/highways-england-triple-deck-roundabout/

Published March 23, 2017. The £75 million Highways England scheme in North Tyneside to create the North East’s first triple-decker junction was 70% complete, with less than a year left on site. The scheme was designed to lower the A19 beneath the A1058 Coast Road and the Coast Road roundabout.

## Bridges and foundations

Since work started in June 2016, three new bridges have been constructed – one to support the A1058 Coast Road over the Coast Road roundabout and two to carry the Coast Road roundabout over the newly lowered A19.

To support the new structures more than 580 piles have been installed, which end-to-end will cover seven miles, and two miles of new drainage.

## Digging the A19 underpass

Crews were removing around 80,000 cubic metres of soil and using it to help form embankments on the nearby A19 Testos scheme. The underpass was designed to let drivers continue straight along the A19 beneath the roundabout.
