Highways England Digs for Victory on £75m Triple-Deck Roundabout

Mar 23, 2017


A major project to create the North East’s first triple decker junction is entering its final stage as work starts to complete the new underpass.


The £75m Highways England scheme in North Tyneside, which will lower the A19 under the A1058 Coast Road and Coast Road roundabout, is now 70% complete with less than a year left on site.

Since work started in June 2016, three new bridges have been constructed – one to support the A1058 Coast Road over the Coast Road roundabout and two to carry the Coast Road roundabout over the newly lowered A19.

To support the new structures more than 580 piles have been installed, which end-to-end will cover seven miles, and two miles of new drainage.

Now around 80,000 cubic metres of soil is being removed and being used to help form the embankments on the nearby A19 Testos scheme.

Highways England assistant project manager Steven Cox said: ‘We are nearly three quarters complete now, with the main bulk of the work digging out the 80,000 cubic meters of soil as the last major milestone.

‘Drivers who use this junction regularly will already be able to see progress as the earth is removed to create the third layer of the junction which will mean drivers will be able to continue straight along the A19 underneath the roundabout.

Click Here To Read The Full Article